Submitted By
Bill McKenna, Village Engineer
Reviewed By
LKS
Agenda Item Title
Title
A Resolution Approving a Contract with J. Nardulli Concrete, Inc. for Project 18-4, 2018 Alley Improvements, in an amount of $2,780,678 and Authorizing its Execution
End
Overview
Overview
Competitive bids were opened on March 1, 2018, for the 2018 Alley Improvement Project 18-4. Thirteen contractors picked up bid documents and eight bids were received. The low responsible bid was submitted by J. Nardulli Concrete, Inc. in an amount of $2,645,832.40. Staff is recommending approving the contract at the available budget amount of $2,780,678, which is higher than the bid amount, in order to get one, or potentially two, additional alleys replaced.
Body
Staff Recommendation
Approve the Resolution.
Fiscal Impact
The costs for this project would be funded through the FY 2018 Capital Improvement Fund, Public Works - Engineering, for Alley Improvements account no. 3095-43780-101-570964; the FY 2018 Capital Improvement Fund, Public Works - Engineering, for Local Street Construction account no. 3095-43780-101-570951 for patching of existing alleys; and through the FY 2018 CDBG fund for Development Customer Services - Neighborhood Services, Capital Improvements account no. 2083-46201-101-583657 according to the table below.
The remaining CIP alley funds will be used to pay for the design of the proposed 2019 alley improvement project which starts typically in late summer.
Awarding at the full budget amount will allow for one, or potentially two, additional alleys to be added to the construction project for replacement.
Residents have the option during the project to reimburse the Village to have their private garage-aprons reconstructed at the contract unit price and this cost will be offset as generated revenue.
Background
This project currently includes rebuilding 23 alley segments throughout the Village. The alleys being replaced under this contract have an average...
Click here for full text