Submitted By
Bill McKenna, Village Engineer
Reviewed By
LKS
Agenda Item Title
Title
A Resolution Approving a Change Order for the Contract with Trine Construction Corp. for Project 18-17, Water and Sewer Main Improvements, and an Amendment to the Contract for an Additional Amount Not to Exceed $191,168 and Authorizing the Amendment's Execution
End
Overview
Overview
Unanticipated additional items and miscellaneous changes to contract quantities on the project # 18-17 Water and Sewer Main Improvement Project will result in the final contract value being over the awarded amount. These items generally include additional work related to relocating the proposed sewer and water mains on North Boulevard due to utility conflicts as well as various changes to the design due to unknown utilities. These changes total approximately $191,168 and adjust the previously approved contract amount of $2,304,749 to $2,495,917.
Body
Staff Recommendation
Approve the Resolution
Fiscal Impact
There are available funds for this change order in the Water and Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements, for Sewer Improvements, account no. 5040-43750-781-570707 which has $2,700,000 available to fund the $191,168 needed for this change order.
Background
The 18-17 Water and Sewer Main Improvement Project on North and South Boulevards is nearing completion with punch list items scheduled to be completed this spring. At the start of construction in the summer of 2018 an existing underground AT&T duct on North Boulevard was found to be in conflict with the proposed location of the sewer main which required relocating both the proposed water and sewer trenches from their originally planned locations. The exact construction costs related to the change in the location of the proposed water and sewer trenches were not fully understood at the time and were thought to be able to be kept within the original contract amount. While preparing paymen...
Click here for full text