Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 19-221    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/22/2019 Final action: 7/22/2019
Title: A Resolution Approving an Amendment to the Contract with K-Five Construction Corporation for Project 19-12, Madison Street Improvements, for Additional Scope of Services to Include Brick Replacement and Landscaping on Madison Street from Humphrey Avenue to Austin Boulevard and Authorizing its Execution
Attachments: 1. Resolution_MadisonStreetAmendment_AdditionalBrickwork, 2. Amendment_K-Five_MadisonStreet_Brickwork_7-8-19, 3. MadisonExhibitAustin, 4. Contract_K-Five_MadisonStreet
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Amendment to the Contract with K-Five Construction Corporation for Project 19-12, Madison Street Improvements, for Additional Scope of Services to Include Brick Replacement and Landscaping on Madison Street from Humphrey Avenue to Austin Boulevard and Authorizing its Execution

End
Overview
Overview
The existing brick sidewalk areas and former landscaped areas along Madison Street from Humphrey to Austin are deteriorated and in need of repairs. The original Madison Street resurfacing and road project did not include scope to beautify and repair this area. Staff is recommending adding scope to the current project for removing all the existing bricks for this roughly one block segment and replacing them with concrete, infilling formerly landscaped dirt areas with new concrete, and replacing missing trees. The work to improve this portion of Madison will cost approximately $125,000. There are available funds in the current construction contract with K-Five to fund this additional scope due to contingencies so a change order will not be required.

End
Body
Staff Recommendation
Adopt the Resolution.

Fiscal Impact
There are available funds for this additional scope within the existing awarded contract with K-Five Construction for this project due to savings and contingencies included in the contract.

Background
The existing brick sidewalk areas behind the curb from Humphrey to Austin are deteriorating and in need of replacement and additional landscaping work to replace trees. The existing bricks between the curb and main public sidewalk were originally installed in the 1980s. The bricks have started to deteriorate and are uneven which create tripping hazards. The original design for this area included landscaped areas in this brick area which have been trampled by pedestrians exiting their cars from the metered parking spaces and are cu...