Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 19-234    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 7/22/2019 Final action: 7/22/2019
Title: A Resolution Approving an Amendment to the Professional Services Agreement Between the Village of Oak park and Clark Dietz, Inc. for Construction Engineering for Project 18-16, Village Hall Parking Lot Improvements Project, to Change the Not to Exceed Amount from $71,857 to $87,875 and Authorizing its Execution as Reviewed at the Village Board Regular Meeting of June 17, 2019.
Attachments: 1. Clark Dietz Resolution, 2. Clark Dietz Amendment, 3. 20190702_Oak Park VH Parking Lot_Cover Letter.pdf, 4. BDE 3608_OakPark_VH ParkingLot_Supplement.pdf, 5. ClarkDietz_Original agreement.pdf
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Amendment to the Professional Services Agreement Between the Village of Oak park and Clark Dietz, Inc. for Construction Engineering for Project 18-16, Village Hall Parking Lot Improvements Project, to Change the Not to Exceed Amount from $71,857 to $87,875 and Authorizing its Execution as Reviewed at the Village Board Regular Meeting of June 17, 2019.

End
Overview
Overview
On June 17, 2019 the Village Board approved a change order to the Village Hall Parking Lot Improvements which also included the direction to bring back a revised contract with the consulting engineering firm on the project, which is this agenda item. In March of 2019 the Village of Oak Park entered into an agreement with Clark Dietz, Inc., to provide construction engineering services for the 18-16 Village Hall Parking Lot Improvements project. Due to delays in the project schedule and additional scope added, additional hours for construction engineering is needed. The amendment of $16,018 adjusts the contract amount to $87,875.

End
Body
Staff Recommendation
Approve the Resolution

Fiscal Impact
In the FY2019 budget there are available funds in the Capital Improvement Fund, Capital Projects, External Support account no. 3095-43780-101-530667.

Background
A change order to the construction contract for Project 18-16, Village Hall Parking Lot Improvements was approved by the Village Board on June 17, 2019 due to unforeseen issues and additional scope that was requested by staff during construction. The change order to the construction contract was needed due to additional work related to patching the underground parking garage, additional waterproofing membrane work on the underground parking garage, additional irrigation work, and additional quantities for various items such as asphalt, curb and sidewalk replacement.

This delay in construction schedule and additional...

Click here for full text