Regular Village Board meetings are typically held at 7:00 p.m., the first three Tuesdays of each month in Council Chambers of Village Hall (room 201), 123 Madison St. When a Regular Meeting falls on a holiday, the meeting typically is held the following night. The Village Board also meets in special sessions from time to time. However, dates and times of Special Meetings can vary and may change.

File #: RES 20-098    Name:
Type: Resolution Status: Passed
In control: President and Board of Trustees
On agenda: 3/2/2020 Final action: 3/2/2020
Title: A Resolution Approving an Amendment to the Contract with Trine Construction Corp. for Project 19-1, Lake Street Sewer and Water Main Improvements, to Change the Not To Exceed Amount from $1,862,000 to $2,190,623 and Authorizing its Execution as Reviewed at the September 9, 2019 Special Meeting
Attachments: 1. Resolution Change Order Lake St W&S, 2. Amendment_Contract_Trine_LakeSt W&S_ChangeOrder, 3. Contract LakeSt WaterSewer19-1
Submitted By
Bill McKenna, Village Engineer

Reviewed By
LKS

Agenda Item Title
Title
A Resolution Approving an Amendment to the Contract with Trine Construction Corp. for Project 19-1, Lake Street Sewer and Water Main Improvements, to Change the Not To Exceed Amount from $1,862,000 to $2,190,623 and Authorizing its Execution as Reviewed at the September 9, 2019 Special Meeting

End
Overview
Overview
As discussed at the September 9, 2019 Board meeting, a change order for the Lake Street Sewer and Water project is required since the project was deferred from 2019 to 2020. The change order reflects the increased costs for materials and labor as well as additional work to replace defective water valves and additional sewer lining. These changes total approximately $328,623 and adjust the previously approved contract amount of $1,862,000 to $2,190,623.

End
Recommendation
Recommendation
Approve the Resolution

Fiscal Impact
There are available funds in the FY2020 Budget for this change order in the Water and Sewer Fund, with the Water and Sewer Fund, Public Works - Water, Water Distribution, Capital Improvements, for water main replacement, account no. 5040-43730-777-570707 providing $208,623 for this change order from projected cost savings in the proposed Augusta Boulevard Water Main Improvement project and the Water and Sewer Fund, Public Works - Sewer, Sewer Collection, Capital Improvements, for sewer main replacement, account no. 5040-43750-781-570707 providing $120,000 for this change order from projected cost savings in the Lemoyne Boulevard sewer project.

Background
As discussed at the September 9, 2019 Board meeting, a change order for the Lake Street Sewer and Water project is required to account for the increased costs for delaying work from 2019 to 2020. The change order accounts for increased labor and material costs and for two items which were not included in the original contract.

The two additional items are replacing a defective wa...